Control Room Video Wall RFP Checklist
A control room video wall request for proposal (RFP) should tell bidders what operators must see, which sources need to appear together and how the wall should behave after a failure. Use this checklist to specify the processor, compare the equipment each bidder includes and tie the accepted proposal to factory and site tests.
Project brief · Supplier response table · Worked example · Award and testing
Attach the project brief and signal schedules
Send the same drawings, signal schedules and operating scenarios to every bidder. Give the package a revision number and assign a stable ID to each requirement. Use Mandatory for an operational need and Optional for a feature you want priced separately.
- Room and wall. State the operator tasks, viewing positions, display layout, rack location and equipment that must stay in service during installation. Identify the type and number of physical display feeds, including any feeds into an LED controller.
- Source schedule. Give each source an ID, interface, expected resolution and refresh rate. For IP sources, give the codec, profile, transport, frame rate and a representative test stream. Include protection requirements where they apply.
- Output schedule. List the output ID, destination, required timing, transport and any extender. Identify who supplies and supports each part of the signal path.
- Preset schedule. For each required scene, give the starting state, window positions, sources shown together, output mapping and operator command. Include the busiest layout and the scene to restore after the specified outage.
Track connected inputs, visible windows, unique IP streams and physical outputs separately. A camera window spanning four LCD tiles can still use one decoded stream while the four tile outputs remain active. Ask the bidder to disclose any resources reserved for preview, transitions or background decoding. Control room video wall design and processor selection
Copy this supplier response table into the RFP
Replace bracketed values with your project criteria. Have each bidder mark the quoted base configuration Meets or Exception. For optional requirements, bidders may also mark Separately priced or Not offered. Where the base bid misses a mandatory criterion, record the exception and show the cost and impact of the proposed remedy.
| ID and priority | Buyer requirement and pass criterion | Bidder status | Quoted equipment and evidence reference | Exception, cost and impact | Verification |
|---|---|---|---|---|---|
| RFP-01 Mandatory |
Display every scheduled output at its required timing. Match the wall drawing and show the numbered test pattern on the assigned endpoints. | FAT / SAT VW-01 |
|||
| RFP-02 Mandatory |
Show the sources in [busiest preset], including [count] distinct IP streams at their scheduled formats, simultaneously. | FAT / SAT VW-02 |
|||
| RFP-03 Mandatory |
From [starting scene], recall [target preset] using the specified operator control. Verify each source, window and output assignment. | FAT / SAT VW-03 |
|||
| RFP-04 [Priority] |
For [listed source transitions], observe [specified outputs]. Record the picture interruption from [start event] to [end event] and check the [limit]. | FAT / SAT VW-04 |
|||
| RFP-05 [Priority] |
After [specified failure and restoration], return to [defined scene] within [limit]. State permitted operator actions and how long the recovered scene must remain stable. | FAT / SAT VW-05 |
|||
| RFP-06 Mandatory |
Deliver the as-built signal map, equipment list, configuration backup, restore instructions and operator training defined in [scope document]. | Site handover VW-06 |
In the equipment column, ask for the chassis, input and output cards, decoder, licenses, firmware assumptions and relevant quantities. Cite a datasheet page, configuration drawing or demonstration record that supports the offered combination. If an external decoder provides one HDMI feed per camera, account for the extra processor inputs, cables, network connections and power.
Ask each bidder to itemize required accessories and licenses, installation, training, support, spares and expansion separately from the base hardware. Request lead time and warranty coverage for the complete proposed system. Confirm who supplies, installs and supports the existing and new components. FOLAIDA video wall processor configurations
Worked example for a six-panel LCD video wall
These are sample buyer requirements. The wall uses three columns by two rows of 1920×1080 LCD panels, each with its own 1080p60 HDMI feed. O1–O3 serve the top row and O4–O6 the bottom row. The signal schedule includes three 1080p60 HDMI sources, H1 (status dashboard), H2 (dispatcher PC) and H3 (briefing PC), plus four distinct 1080p30 H.264 camera streams, C1–C4.
| Preset | Window placement | Visible windows | Distinct IP feeds shown | Active outputs |
|---|---|---|---|---|
| Overview | O1 H1, O2 H2, O3 C1, O4 C2, O5 C3, O6 C4 | 6 | 4 | 6 |
| Incident | C2 spans O1, O2, O4 and O5. O3 shows H3 and O6 shows H1. | 3 | 1 | 6 |
For RFP-02, the Overview scene needs all four camera streams at once. A bidder offering two simultaneous decodes in the base configuration should mark Exception, identify a priced configuration that supports four, and supply evidence for its exact hardware and licenses. Review that revised configuration before award. Verify it with representative streams at the factory and production streams on site under test VW-02.
For RFP-05, the buyer might require the processor to restore Overview after a processor-only power interruption. Leave the displays, sources and network powered. Start timing when processor power is restored. All six windows must return automatically to their assigned outputs and complete ten consecutive seconds of stable display within 90 seconds. Repeat three times and record the slowest result and the evidence under VW-05. Set the actual outage scenario and limit with the operations team.
Compare the offers and carry approved requirements into FAT and SAT
- Review mandatory exceptions first. Resolve each exception in writing with its technical and commercial impact. Confirm which equipment, licenses and services the accepted price covers.
- Run the same demonstration for each finalist. Give bidders the same source formats, preset schedule and starting conditions. Ask them to identify differences between the demonstration setup and the proposed installation.
- Carry the same IDs into the test plan. For example, RFP-02 maps to VW-02 at both factory acceptance testing (FAT) and site acceptance testing (SAT). Agree on allowable factory substitutions, site retests and the required evidence before shipment.
The Fayetteville Public Works Commission’s video wall upgrade tender provides a public example of requesting technical documentation and reviewing a demonstration, pricing, training and support. AVIXA’s performance verification guidance covers what to verify, when to verify it and how to report the outcome. Public video wall tender · AVIXA performance verification
Use your approved equipment list and requirement IDs to create the test runs and sign-off records. Video wall processor FAT/SAT acceptance test template
Send the wall drawing, source schedule and busiest preset when requesting a configuration review. Contact FOLAIDA